Below is the summary for this period:

  • RoW permit obtained
  • Demolition of sidewalk and asphalt. Removal of fence panels and under rocks.
  • Setup traffic control barricades.
  • Water line tap into the 8 inch city water line.
  • Install saddle and RPZ and meter box
  • Copper lines installed
  • Flowable fuel pour, asphalt patched.
  • Refill digs, clean street. Reinstall fence panels.
  • Compact asphalt patch.
  • Moisture and density test passed. DMM will provide report from GeoScience