Summary of construction progress for this period.

  • CW approved all water tap corrected plans.
  • Added elevation by putting dirt. The foundation pod has been elevated by 2-3 feet to level it with the side walk.
  • Foundation work has began.
  • Got structural sub drawing approved from Paramount Engg.
  • Got surveyor to mark building corners and elevator points. Got approval from the Architect and the Structural Engg.