Below is the summary of the construction progress during this period.

  • Got approval for public works.
  • All fire line private inspection passed.
  • Back filled all trenches and basketball court
  • Removal of large rocks took more time and resources than originally estimated.
  • Final steel shop drawings are awaiting feedback from structural engineer.